Integration Management
Cash-Flow Analysis Techniques
Project Selection Criteria
|
What is it
|
Selection Mechanism
|
Payback Period
|
Period of time required to recoup the funds expended in an investment, or to reach the break-even point.
|
Select Lowest
|
Internal Rate of Return (IRR):
Think bank Interest rate
|
Internal portfolio rate at which the investment will produce results.
|
Select Highest
|
Net Present Value:
Money now is more valuable than money later on.
|
Formula:
PV = FV/(1 + r)t
Where
r =interest rate
PV – Present Value
FV = Future Value
t = Time period
|
Select Highest
Remember the Formula!!
|
ROI
Return on Investment
|
Divide net profit by total assets
|
Select Highest
|
Benefit Cost Ratio
|
Benefit / Cost
|
Select Highest
|
Cost Management
Rough Order of Magnitude estimate (ROM) = -25% to +75%
Definitive estimate = -5% to +10%
Earned Value Management Formulas:
Name
|
Formula
|
What is it?
|
Interpretation
|
|
BAC
|
Budget at Completion
|
No formula
|
Approved Budget
|
|
PV
|
Planned Value
|
PV = BAC* Planned % Complete
|
What your schedule says you should have spent
|
|
EV
|
Earned Value
|
EV = BAC * Actual% Complete
|
How much of the project’s value you’ve really earned
|
|
AC
|
Actual Cost
|
No Formula
|
Spending on the projects – actual
|
|
SPI
|
Schedule Performance Index
|
SPI = EV/PV
|
Whether you’re behind or ahead of schedule
|
SPI >1 – Ahead of Schedule
SPI = 1 – As per Schedule
SPI < 1 – Behind Schedule
|
SV
|
Schedule Variance
|
SV = EV-PV
|
How much ahead or behind schedule you are
|
|
CPI
|
Cost Performance Index
|
CPI = EV/ AC
|
Whether you’re within your budget or not
|
CPI >1 – Under Planned Budget
CPI = 1 – On Budget
CPI < 1 – Over Planned Budget
|
CV
|
Cost Variance
|
CV = EV – AC
|
How much above or below your budget you are
|
|
EAC
|
Estimate at Completion
|
EAC = BAC/CPI
Mostly Used
|
The expected total cost of completing all work.
If the CPI is expected to be the same
|
|
EAC
|
Estimate at Completion
|
EAC=AC+BAC–EV
|
If future work will be accomplished at the planned rate
|
|
ETC
|
ETC = EAC – AC
|
The expected cost to finish remaining work
|
||
TCPI
|
To Complete performance Index
|
TCPI=(BAC-EV)/(BAC-AC)
|
The run rate required to win the match
(Run rate = spending rate)
(Target Runs = Approved Budget)
|
|
Three-Point Estimates:
PERT Analysis Also called BETA Distribution
Mean = (P + M + O)/3
Triangular Distribution Also called Average Distribution
Mean = (P + 4M + O)/ 6
Quality Management
1 Sigma = 68.26%
2 Sigma = 95.46%
3 Sigma = 99.73%
6 Sigma = 99.99%
Pareto Rule = 80/20
Communication Management:
Communication channels = n * (n-1)/2
Where n is the number of stakeholders
Procurement Management
Make or Buy Decision:
Make or Buy Decision: Select decision which result in lower cost or lower risks.